L-83 Boilermakers shine on Jeffrey Energy Center outages

[+]Enlarge

Boilermakers position a reheat outlet header onto a trolley assembly. Left to right, Vitaliy Shevchenko, Vasiliy Shevchenko, Charlie Clark, Jared Brindley and Wade Adams.

[+]Enlarge

Westar’s Jeffrey Energy Center, St. Marys, Kansas.

[+]Enlarge

L-83 members from the day shift working on Unit 1.

[+]Enlarge

L-83 members from the day shift working on Unit 1.

[+]Enlarge

L-83 members from the night shift working on Unit 1.

[+]Enlarge

Crew members disconnect rigging following a successful lift to the penthouse platform.

[+]Enlarge

Rodney Hale lowers an air heater basket to other Boilermakers four stories below.

[+]Enlarge

A new reheat outlet header section rests inside the penthouse before positioning and welding.

[+]Enlarge

Jared Hogue (top) and Clayton Adams pull air heater baskets from a radial heater assembly. About 1,000 of the baskets will be replaced on Unit 1.

Members replace re-heat outlet headers, air heater baskets

LOCAL 83 (KANSAS CITY, MISSOURI) Boilermakers employed by Day & Zimmermann are demonstrating their skills at Westar Energy’s Jeffrey Energy Center in St. Marys, Kansas, where crews are working the spring outage on Unit 1. The job follows on the heels of the Unit 2 fall outage, successfully completed late last year. Jeffrey Energy Center is the largest fossil power generation plant in Kansas, with three units rated at a combined 2,155 MW.

The Unit 1 outage mirrors work performed on Unit 2, including the replacement of re-heat outlet headers and air heater baskets as well as ancillary repairs to the boiler and other components. Boilermakers worked more than 100,000 man-hours on Unit 2 and are expected to work a similar number on Unit 1.

Replacing the old header sections, each weighing some 36,000 pounds, required use of a 500-ton hydraulic crane positioned below the penthouse of each unit. Following the 200-foot lifts, Boilermaker crews moved the new headers into place using a series of trolleys and air hoists.

On Unit 2, over 1,700 terminal tube welds were made, along with 28 6-inch riser tube welds, two 26-inch welds, and two 30-inch link connection welds. Crews achieved a weld rejection rate of just 1.6 percent, and the header project remained on schedule or slightly ahead of schedule from start to finish.

Welding on the new Unit 1 headers began in late March.

On the Unit 2 fall outage, Boilermaker crews pulled and replaced more than 1,000 air heater baskets while also making repairs to the air heater system. The same work is currently under way on Unit 1.

Bull steward Mark “Shoe” Shoemaker praised Boilermaker crews and commended Day & Zimmermann and Westar engineers who worked months in advance to plan the outages and choreograph critical work such as the header change-outs. “A job is successful for many reasons — sound planning, solid leadership, working the plan, teamwork, communication and skilled men and women who know their job and perform it safely,” he said.

Shoemaker added, “With all the environmental regulations and competition from other sources of electricity, it is reassuring to see power plant owners making upgrades to their coal-fired units.”

Day & Zimmermann Site Manager Ryan Statler said, “We’ve got a great set of Boilermakers from Local 83. They’re top-notch guys. They do it right the first time. Together, we attack [the project] as a team and do it safe and on time.”

Photo Gallery

Tags  Jobs
Locals  L-83
Reporter  V56N1
Published on the Web: April 18, 2017

Latest News

  • Ed Atwood solicits comments from former Boilermakers who worked on the Gateway Arch project in the 1960s.

    Former L-659 members create ‘baby’ Gateway Arch

    Read More

  • International staff and L-S234 volunteers participate in an internal organizing drive for Tennsco workers.

    Organizers add 78 members to L-S234

    Read More

  • U.S. Air Force Maj., retired, Brian Shul describes his experience flying the SR-71 Blackbird spy plane.

    Industrial Sector leaders meet in Las Vegas

    Read More

  • Newton B. Jones, Intl. President

    It’s time to replace Clean Power Plan with a sensible solution

    Read More

  • Setting The Record Straight On The Jones Act

    Read More